 Systematic Effects - Brendan Crill Systematic Effects - Brendan Crill
  
-CoSigning the Report +__CoSigning the Report__ 
---------------------+
 When the report is mature we will circulate a final draft and you will have an opportunity to CoSign before it is submitted to NASA. When the report is mature we will circulate a final draft and you will have an opportunity to CoSign before it is submitted to NASA.
  
-The Report and Decadal Science White Papers +__The Report and Decadal Science White Papers__ 
--------------------------------------------+
 As you may know, there is a project-independent effort ongoing to write and submit Science White Papers to the Decadal Panel.   The deadline is in early January. This effort transcends PICO, CMB-S4, or other specific projects. Hence, the PICO report is separate. We expect that NASA will forward the PICO report to the Decadal Panel in conjunction with delivery of other project-related white papers in mid-2019. As you may know, there is a project-independent effort ongoing to write and submit Science White Papers to the Decadal Panel.   The deadline is in early January. This effort transcends PICO, CMB-S4, or other specific projects. Hence, the PICO report is separate. We expect that NASA will forward the PICO report to the Decadal Panel in conjunction with delivery of other project-related white papers in mid-2019.
  
-Instrument Update +__Instrument Update__ 
------------------+
 The architecture of the instrument hasn't changed since early summer. We now have a final required specifications and final best case performance estimate (also known as 'goals'). The one number summary is that the required depth is 0.87 uK*arcmin, and goal is 0.61 uK*arcmin, both are for full sky coverage. The architecture of the instrument hasn't changed since early summer. We now have a final required specifications and final best case performance estimate (also known as 'goals'). The one number summary is that the required depth is 0.87 uK*arcmin, and goal is 0.61 uK*arcmin, both are for full sky coverage.
  
-Final Engineering Review and Cost Estimate +__Final Engineering Review and Cost Estimate__ 
-------------------------------------------+
 Our colleagues at JPL will finalize the mission's engineering documents by the end of October. Some of the contributions will enter into the report, others will accompany the report as a set of slides. As reported in the past, the mission is costing within the $1B cap, with some margin. Our colleagues at JPL will finalize the mission's engineering documents by the end of October. Some of the contributions will enter into the report, others will accompany the report as a set of slides. As reported in the past, the mission is costing within the $1B cap, with some margin.
  