Line 21: | Line 21: | ||
* Independent Cost Estimate does not include pre-phase A technology maturation costs, but we should be careful about including too many low maturity technologies to avoid large cost penalties. | * Independent Cost Estimate does not include pre-phase A technology maturation costs, but we should be careful about including too many low maturity technologies to avoid large cost penalties. | ||
* Imager WG Update (Shaul) | * Imager WG Update (Shaul) | ||
+ | * first draft baseline imager (optics/ | ||