Campuses:
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revision | |||
private:teleconsnotes20180228 [2018/02/28 13:46] – hanany | private:teleconsnotes20180228 [2018/02/28 15:59] (current) – kyoung | ||
---|---|---|---|
Line 1: | Line 1: | ||
====== Telecon Notes February 28, 2018 ====== | ====== Telecon Notes February 28, 2018 ====== | ||
- | Attendance: | + | Attendance: |
- | Notes by: | + | |
+ | Notes by: Karl | ||
=== Agenda:=== | === Agenda:=== | ||
Line 15: | Line 16: | ||
* Possible White papers | * Possible White papers | ||
* individual vs Collated | * individual vs Collated | ||
+ | |||
+ | |||
+ | === Notes === | ||
+ | |||
+ | May Workshop | ||
+ | * Fundamental Physics | ||
+ | * de Gouvea confirmed | ||
+ | * Vera Gluscevic -- **Lloyd** will check in. | ||
+ | * Tracy Slatyer invited, **Lloyd** will follow up. | ||
+ | * Panel: 3 confirmed, **Lloyd/ | ||
+ | * Axion DM: invited Dan Grin, he's considering. | ||
+ | * Extra-galactic Science | ||
+ | * replace Simone. | ||
+ | * Panel: all invited. | ||
+ | * Galatic Science | ||
+ | * all confirmed. | ||
+ | * waiting to add a foregrounds person | ||
+ | * Panel: Giles still considering. | ||
+ | * Tech | ||
+ | * Panel: Adrian pinged, waiting to invite others. | ||
+ | * Final session | ||
+ | * Moderated by Lloyd. | ||
+ | * Al can't commit. 1:3 chance could come, shipping Piper. | ||
+ | * Bill in similar case, trying to make schedule work. | ||
+ | * Suzanne pinged again. | ||
+ | * Lloyd/Shaul to work offline to find more people. ideally S4 person, outside person, | ||
+ | * Charles: Planck people relevant. volunteering if needed. | ||
+ | * Looking for outside people with other input. | ||
+ | |||
+ | Science Team Costs (Al, Charles) | ||
+ | * for TeamX and mission costs | ||
+ | * basic number of people and cost per person | ||
+ | * manpower spread evenly over all years, ignores ramp up. | ||
+ | * 4 yrs flight, 4yrs I&T, 2 yrs post flight analysis | ||
+ | * adjusted to 7.5 to account for ramp up. | ||
+ | * $52 M total, no reserves (close to 12% of WB lines 5-6, which is common rule of thumb advice.) | ||
+ | * Charles: US planck involvement. including early release source catalog cost. real year dollars. total cost for data analysis ends up $80-85 M. $52 is none too high, but probe is competed line so be careful. | ||
+ | * CL: for example. include inflation. Planck #s include multiple (3) extended missions by senior review. those don't go in initial proposal. | ||
+ | * CL: in report, data analysis is big part of the program. | ||
+ | * CL: having second thoughts about my numbers. | ||
+ | * Lloyd: rich data set. need to weight analysis heavily. | ||
+ | * Shaul: makes sense. need to remember this goes against other costs. | ||
+ | * Shaul: large unknowns are mission, I&T, spacecraft. | ||
+ | * SH: JPL contracted with Lockheed to cost spacecraft bus for TeamX. | ||
+ | * SH: thermal design passed to Goddard | ||
+ | * CL: data analysis carried about 5% reserves for Planck. | ||
+ | * Al: reasonable. | ||
+ | * CL: can also split science costs around. for example can split 3 month in flight CVP out. can be own category. | ||
+ | |||
+ | Engineering documents, | ||
+ | * SH: JPL TeamX slides exist. not ITAR approved for broad release. | ||
+ | * AT+SH: talked with headquarters to do something different. | ||
+ | * Al: raw teamX seems crazy. | ||
+ | * SH: rule was ' | ||
+ | * Al: My experience with Goddard MDL was those reports going only to PI. | ||
+ | * SH: agree TeamX (or MDL) are geared to give suggestions to PI. | ||
+ | * CL: Goddard doing 5 studies, JPL doing 5. should be some agreement on what to send. Jeff Booth person at JPL in charge of 5. Agreement of what to send should be global. | ||
+ | * SH: That was my argument! | ||
+ | * CL: I will talk to Jeff also. | ||
+ | * SH: often get 'you have 50 pages' as a response. but we want those to be mostly science. 50 pages is for decadel panel so needs to be science. | ||
+ | * Al: tying budget numbers to recent flights as much as possible would be good idea. tying ' | ||
+ | |||