Campuses:
This shows you the differences between two versions of the page.
| Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
| systematicswg:telecons:2018-06-18:start [2018/06/18 11:06] – bcrill | systematicswg:telecons:2018-06-18:start [2018/06/18 12:02] (current) – bcrill | ||
|---|---|---|---|
| Line 1: | Line 1: | ||
| - | online: Eric, Brendan, Shaul | + | online: Eric, Brendan, Shaul, Maurizio |
| Agenda | Agenda | ||
| * Updates | * Updates | ||
| - | * Do we have simulated main beams? Eric wants to take a look at the cross-polar beam. | + | * Do we have simulated main beams? Eric wants to take a look at the cross-polar beam. |
| + | * Eric recently learned that in Litebird, the peak of the U beam for GRASP sims of the main beams is something like 10% of the peak of the I beam map. This is much larger than simulations for Planck HFI and LFI (which was < 1% peak) and was thus determined to not be a problem. | ||
| + | * There are two effects: 1. Calibration will correct any " | ||
| + | * Can we find a main lobe GRASP simulation for PICO that we can look at? Eric can determine whether the cross-polar response can be corrected by a simple calibration factor. | ||
| + | * action to Eric: to describe this in more detail next week (building on his previous post). | ||
| + | * action to Shaul: talk to Karl to look at main beam GRASP sim for two orthogonal detectors. | ||
| + | * Maurizio worked with Andrea. | ||
| + | * Maps are available for 2 year simulation requested by Kris: / | ||
| + | * Andrea was able to patch toast to bring in dacapo input. Allows gain estimation sims: 1. a map of the full sky reconstructed over 2 years and 4 detectors, 2. gain factors vs. time, and 3. a map that has the effects of residual gain errors. | ||
| + | * Maurizio can use these products to compute angular power spectra and show the science impact of the residual gain errors. | ||
| * Systematics section outline | * Systematics section outline | ||
| + | * Shaul wants to have a draft PICO report by September 1. The real one will be submitted to NASA in December | ||
| + | * Write a systematics paper? Is there anything particularly new in the PICO material? | ||
| + | * ideas for Maurizio' | ||
| + | * Eric's particular work is mostly a specific application of previous methods. | ||
| + | * PICO has a different scanning strategy from Litebird and CORE. | ||
| + | * Sidelobe pickup given the telescope is interesting: | ||
| + | * Brendan to make an outline for paper. | ||
| + | * Note: Brendan to be on vacation for 2 weeks. will be back for July 9 telecon. | ||
| + | * Eric will be gone Late July - early August. | ||
| + | | ||
| + | |||