On the call:

Agenda
  • FSL progress
    • Made reasonable beams. More of the central peak needed to be masked out. At ell of a few 100 only about 45 dB of variation between the main beam and the rest of the map can be reconstructed. Noise level of the final maps is about 10^-6, maximum of the final map is 2.5×10^-2.
    • grasp fullsky mainbeam, masked combined beams, stokes reconstructed alms
  • Gain error figures for report
  • Merge all systematics figures into a single one?
  • Report draft systematics.pdf
systematicswg/telecons/2018-10-08/start.1539012617.txt.gz · Last modified: 2018/10/08 10:30 by kyoung