===== Agenda for May 27, 2010 ===== === Cost and Schedule === * New Plan - Understand that Module ready by 2017 => no screening until 2019 * Procure and deploy screeners early as part of DULBCF * Build up staff and screen 2011 - 2019 * Create integration of Davis, LBL, Soudan with a surface facility at USD (Keenan head) * Need more money for this! Need Plan - Physics Frontier Center? * Move already bought screeners into FAARM - schedule moves for uninterrupted screening (except one very sensitive screener will move early and monitor all activities, including tank fill) * FAARM is the active shielding, infrastructure, and immersion tank * Any other specialty screeners (what about radon emanation? early or late?) * Reflect this new plan in Microsoft Project (Lee Petersen) === New Layout === * {{http://zzz.physics.umn.edu/lowrad/engineering/concept|see latest here}} * Plastic removed from under torus * questions of floor height and opening not resolved * need to understand acrylic options - should we bring in other engineers? other companies? * Any news from Dufrane? === Screener Group === * Not much heard from groups in response to DUSEL poll * Screener group (Richard?) needs to gather info by ISE and post to [[groups:screenwhite|Screening Working Group White Paper]] by next meeting * I will call each group afterward to solicit further info and to solidify support for DULBCF === Immersion Tank === * posted first pass on wiki: needs more detailed schedule and cost === short term plans for this summer === * Nail down the schedule for the Mid-July for undergrads from U Minn, SD, BHSU * Need place to stay - Kara said she would find one