Agenda for April 8, 2010

Integration

Refine cost and schedule
Improve the conceptual design of the FAARM
Implement information from other working groups

Water Shield

Make it real, talk to companies, do the engineering e.g.
Develop infrastructure into shield (ductwork, electrical etc)

Screener Group

Work with Yuen-Dat to compile results of survey
Define parameters of shielding and common elements between screeners
Plan for screening at Sanford and schedule of installation and move

Immersion Tank

Continue cost and schedule for CTF
compile relevant sections of survey (poll community about the functionality of the ultra sensitive screener

Characterization

short term plans for this summer - involve other groups
long term plans for neutron work