==== 2012 Engineering Plans for a Site-independent FAARM to fit in Homestake or Soudan ==== | ==== 2012 Engineering Plans for a Site-independent FAARM to fit in Homestake or Soudan ==== | ||
=== Overview === | === Overview === | ||
- | Project Description (Lee Petersen)\\ | + | Three-Dimensional Renderings of entire facility {{:: |
+ | Project Description (Lee Petersen){{:: | ||
Project Participants are Itasca, CNA, Miller Dunwiddie, Dunham Associates.{{: | Project Participants are Itasca, CNA, Miller Dunwiddie, Dunham Associates.{{: | ||
- | FAARM Renderings\\ | + | ** Budget |
- | Budget\\ | + | {{: |
- | {{: | + | {{:: |
===Architectural Design === | ===Architectural Design === | ||
* {{:: | * {{:: | ||
* {{: | * {{: | ||
* {{: | * {{: | ||
- | | + | === Acrylic Torus Engineering === |
+ | | ||
+ | * Drawing sent to Manufacturer for cost estimate | ||
+ | * {{:: | ||
+ | * {{:: | ||
=== Electrical Systems === | === Electrical Systems === | ||
* {{: | * {{: |