This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
planning [2011/03/26 12:45] – [Gravity Meter] engel014 | planning [2011/05/09 12:33] (current) – [Gravity Meter] 24.245.16.19 | ||
---|---|---|---|
Line 5: | Line 5: | ||
Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum. | Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum. | ||
+ | **update Monday, April 18 --** | ||
+ | Full Power was restored to the lab over the weekend. | ||
==== CoGeNT ==== | ==== CoGeNT ==== | ||
=== Immediate needs === | === Immediate needs === | ||
Nitrogen purge for radon reduction (LN boiloff or N2 compressed gas) | Nitrogen purge for radon reduction (LN boiloff or N2 compressed gas) | ||
+ | |||
+ | When switching off power to the experiment, please preserve an AC ground (i.e., do not allow CoGeNT electronics to " | ||
+ | |||
=== Plan for startup === | === Plan for startup === | ||
+ | |||
+ | As soon as is possible, please flush room-temperature gas (preferably compressed nitrogen, but any other *moisture-free* gas will do) through the input to the detector Dewar, presently attached to a 200 liter LN2 tank. Do so (at low flow, over one or two days) until the temperature of the gas coming through the latex hose exhaust is measured to be room temperature. Please do not alter (at all) the position of the thermocouple inserted into that exhaust when measuring this temperature. Because the detector cold finger does not reach the bottom of the detector Dewar, and the Dewar is new and carefully sealed, there is not much of a heat load to the bottom ~1/3 of the LN2 presently in there. If this procedure is not performed, that bottom layer could stay there for a number of weeks, keeping the detector from truly thermalizing at room temperature, | ||
+ | |||
+ | Please contact us about ten days before the date when you envision being able to receive one of us in the lab to restart the experiment, also foreseeing continued LN2 availability (must have that before we can think of restarting). We'll have a few more instructions for preparation then. THANKS. | ||
==== SOLO ==== | ==== SOLO ==== | ||
=== Immediate needs === | === Immediate needs === | ||
Nitrogen purge for radon reduction (LN boiloff or N2 compressed gas) | Nitrogen purge for radon reduction (LN boiloff or N2 compressed gas) | ||
=== Plan for startup === | === Plan for startup === | ||
+ | * Require pictures of the area to show debris | ||
+ | * Determine if vacuum space requires repumping. Where is the vacuum port? Inside or outside of shield? | ||
+ | * If outside, definitely pump | ||
+ | * Proceed after lab has been cleaned | ||
+ | * Wipe down Mylar | ||
+ | * Restart LN, bias, take initial background spectrum | ||
+ | * If this is OK, proceed with regular operation | ||
+ | * If background shows contamination, | ||
+ | * Retake background spectrum | ||
+ | * If background still shows contamination, | ||
==== Gopher ==== | ==== Gopher ==== | ||
=== Immediate needs === | === Immediate needs === | ||
Line 19: | Line 38: | ||
==== Neutron Multiplicity Meter ==== | ==== Neutron Multiplicity Meter ==== | ||
=== Immediate needs === | === Immediate needs === | ||
+ | No immediate needs... the detector should have weathered the loss in power relatively unharmed. | ||
=== Plan for startup === | === Plan for startup === | ||
+ | Once we have power, I will need some on-site assistance in turning our DAQ computers & electronics back on. We will need to assess the state of the three UPS backups... provided the backups can still provide power to their respective components, the experiment should be operable again almost immediately. | ||
==== Veto Shield ==== | ==== Veto Shield ==== | ||
=== Immediate needs === | === Immediate needs === | ||
+ | Make sure that the HV is all off while power is intermittant. | ||
+ | |||
+ | We would like to have the 5 veto computers up and running as soon as possible, so we can continue our DAQ work. The question is when will the network be up, so we can use them remotely? | ||
+ | |||
+ | Once there is network functionality, | ||
+ | * deactivate the LabView License | ||
+ | * transfer data and software files to TwinCities | ||
+ | * debug the ADC library software for the HV remote control & readback in order to duplicate it here | ||
+ | |||
+ | Other jobs which could be done in the first week with minimal power are | ||
+ | * order Ar, CO2 gas for the shield | ||
+ | * order more hydrogen for the mixer - it is getting very low | ||
+ | |||
=== Plan for startup === | === Plan for startup === | ||
+ | When there is power for the pumps, then the gas rack and gas mixer should be turned on and tested. | ||
==== Reeves Electroforming ==== | ==== Reeves Electroforming ==== | ||
=== Immediate needs === | === Immediate needs === | ||
=== Plan for startup === | === Plan for startup === | ||
==== Gravity Meter ==== | ==== Gravity Meter ==== | ||
- | If it is necessary to move the gravity meters then they should be clamped first. | + | === Immediate needs === |
- | === Immediate needs === | + | === Plan for startup === The start up has been accomplished |
- | Restart the two gravity meters and adjust the long and cross levels. | + | |
- | === Plan for startup === | + | ==== Update from Marvin Marshak (Saturday, April 16) ==== |
- | Whenever possible, I would like to bring the meter that is supported | + | |
- | ==== Update from Marvin Marshak (Friday, March 25) ==== | + | |
- | There was continued work in the shaft today and a brief entry into the Soudan | + | • Full electrical power was restored to the entire |
- | + | DNR staff and an outside electrical contractor installed a new power cable | |
- | * Today' | + | between |
- | + | all circuits in the lab were shut off. Following this check, power was turned | |
- | * The electrical cable between | + | on to the Lab substation |
- | + | and HVAC system in the Lab. These systems appear to function normally. | |
- | | + | The Lab closed loop cooling system also seems to function normally. |
- | + | The Lab fire detection system is also functioning and will shut down power | |
- | * All doors to the lab are now closed at the suggestion | + | to the lab, in the event of an alarm detection. |
- | + | ||
- | * The DNR and University staff have now worked continuously since last Thursday night. There will be no work this weekend, in order to rest the staff for next week. Work will resume | + | • The fiber optic cable has sufficient slack that it will be possible to cut out |
- | + | the damaged section | |
- | * Next report will be Monday. | + | be working next week. |
+ | |||
+ | • Representatives of cleaning companies will visit the lab on Monday to | ||
+ | prepare estimates for general clean up of the lab, including remnants | ||
+ | of the foam and the debris brought in by the foam. | ||
+ | |||
+ | • ECI, the contractor hired by the DNR to do shaft renovations, | ||
+ | key personnel on site this coming week, beginning with an on-site pre-construction | ||
+ | meeting on Monday. CNA Engineering has also been hired to provide | ||
+ | geo-technical advice to ECI. A CNA engineer | ||
+ | coming week. A likely arrangement beginning this coming week is that | ||
+ | lab and DNR access | ||
+ | at 6 am, with ECI shaft work on a second shift, possibly beginning at 2 pm. | ||
+ | |||
+ | • Work in the lab this coming week will focus on re-starting the MINOS | ||
+ | Detector, beginning with checks of control system electronics and work | ||
+ | to dry out the magnet cables. | ||
+ | |||
+ | • The sprinkler contractor has submitted drawings | ||
+ | Marshal for the repairs | ||
+ | and repair work is also expected to start this coming week. | ||
+ | |||
+ | • The University has hired CNA Engineering and Don Zeni, a specialized drilling | ||
+ | consultant, to evaluate the feasibility of providing an alternate | ||
+ | lab through either a ~6 inch diameter hole and/or a ~4 foot diameter hole. | ||
+ | A small hole would enable an independent path for communications, | ||
+ | high pressure air ventilation between the surface and the lab. The larger | ||
+ | hole would also enable a secondary, emergency egress, in addition to the telecom | ||
+ | and power connections. |