Go to the U of M home page
School of Physics & Astronomy
Assay and Acquisition of Radiopure Materials

User Tools


planning

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revisionPrevious revision
Next revision
Previous revision
planning [2011/04/01 10:52] – [Experimental Needs] 128.101.214.112planning [2011/05/09 12:33] (current) – [Gravity Meter] 24.245.16.19
Line 5: Line 5:
 Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum.  Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum. 
  
-**update Friday April 1st  --**   +**update Monday, April 18  --**   
-No one underground today. Power in the lab is minimal until power feed repaired.  Nitrogen purges are going on all experiments and will last through next week without intervention.  +Full Power was restored to the lab over the weekend.  Cleaning crews and fiber optic cable splicing will occur through this week.  Computers will become available for remote access by the end of the week.  Currently expecting access may be as soon as mid-May, but we need to properly schedule visits, so we will being communicating directly with the experiments about their visits near the end of April.
 ==== CoGeNT ==== ==== CoGeNT ====
 === Immediate needs === === Immediate needs ===
Line 62: Line 62:
 === Plan for startup === === Plan for startup ===
 ==== Gravity Meter ==== ==== Gravity Meter ====
-If it is necessary to move the gravity meters then they should be clamped first. +=== Immediate needs ===  
-=== Immediate needs === +=== Plan for startup === The start up has been accomplished by Jerry Meier.  A replacement UPS power supply is being shipped to the Surface Building in Soudan for installation in the gravity meter setup. 
-Restart the two gravity meters and adjust the long and cross levels. + 
-=== Plan for startup === +==== Update from Marvin Marshak (SaturdayApril 16) ==== 
-Whenever possible, I would like to bring the meter that is supported by foam back to my home.  If I am allowed to bring the instrument to the surface then I can come any time.  If someone else does this then the meter should be clamped first and I can meet them at the surface+ 
-==== Update from Marvin Marshak (WednesdayMarch 30) ====+ 
 +• Full electrical power was restored to the entire Soudan Laboratory TODAY. 
 +DNR staff and an outside electrical contractor installed a new power cable 
 +between the 22nd and 27th levels. Lab staff then checked to be sure that 
 +all circuits in the lab were shut off. Following this check, power was turned 
 +on to the Lab substation via the new cable. Lab staff then turned on the lights 
 +and HVAC system in the Lab. These systems appear to function normally. 
 +The Lab closed loop cooling system also seems to function normally. 
 +The Lab fire detection system is also functioning and will shut down power 
 +to the lab, in the event of an alarm detection.
  
-Work at Soudan continued today in both the shaft and the lab.+• The fiber optic cable has sufficient slack that it will be possible to cut out 
 +the damaged section and re-splice the cable. The splicing contractor will 
 +be working next week.
  
-• Dan Bauer and Jim Beaty completed work today to stabilize the CDMS Detector.+• Representatives of cleaning companies will visit the lab on Monday to 
 +prepare estimates for general clean up of the lab, including remnants 
 +of the foam and the debris brought in by the foam.
  
-• New electrical cable to provide full power for the lab and the 27th +• ECI, the contractor hired by the DNR to do shaft renovations, will have 
-level pumps was ordered for delivery Thursday next week.+key personnel on site this coming week, beginning with an on-site pre-construction 
 +meeting on Monday. CNA Engineering has also been hired to provide 
 +geo-technical advice to ECI. A CNA engineer will also be on site this 
 +coming week. A likely arrangement beginning this coming week is that 
 +lab and DNR access to the mine will occur on a first shift, possibly beginning 
 +at 6 am, with ECI shaft work on a second shift, possibly beginning at 2 pm.
  
-• DNR electricians installed new communications connections +• Work in the lab this coming week will focus on re-starting the MINOS 
-to the 27th level shaft station.+Detector, beginning with checks of control system electronics and work 
 +to dry out the magnet cables.
  
-• Rock removal continued in the shaft. Another new steel +• The sprinkler contractor has submitted drawings to the University Fire 
-reinforcing beam was installedAn outside engineering +Marshal for the repairs to the sprinkler systemApproval of the drawings 
-consultant visited Soudan and inspected the shaft. The consultant +and repair work is also expected to start this coming week.
-recommended that loose rock removal and shaft repairs +
-continue with high priority.+
  
-• Operations in the MINOS Lab today focused on restoring +• The University has hired CNA Engineering and Don Zeni,  a specialized drilling 
-operation of monitoring and alarm systems. Outside experts +consultant, to evaluate the feasibility of providing an alternate access to the 
-are scheduled to visit the lab this week to check out the MINOS +lab through either a ~6 inch diameter hole and/or a ~4 foot  diameter hole. 
-electrical supply system, the lab fire alarm system and the +A small hole would enable an independent path for communicationspower and 
-hard-wired telephone lines.+high pressure air ventilation between the surface and the lab. The larger 
 +hole would also enable a secondary, emergency egress, in addition to the telecom 
 +and power connections.
  
planning.1301673129.txt.gz · Last modified: 2011/04/01 10:52 by 128.101.214.112