Campuses:
This shows you the differences between two versions of the page.
Both sides previous revisionPrevious revisionNext revision | Previous revision | ||
planning [2011/04/01 10:54] – [Experimental Needs] 128.101.214.112 | planning [2011/05/09 12:33] (current) – [Gravity Meter] 24.245.16.19 | ||
---|---|---|---|
Line 5: | Line 5: | ||
Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum. | Please feel free to login (first time will create account) and edit your section. I have put a few placeholders to show how this might work. Immediate needs refers to jobs you would like done by the mine crew as soon as there is any access. I have already communicated the need for SOLO, Gopher, and CoGeNT to keep radon plateout to a minimum. | ||
- | **update | + | **update |
- | No one underground today. | + | Full Power was restored to the lab over the weekend. |
==== CoGeNT ==== | ==== CoGeNT ==== | ||
=== Immediate needs === | === Immediate needs === | ||
Line 62: | Line 62: | ||
=== Plan for startup === | === Plan for startup === | ||
==== Gravity Meter ==== | ==== Gravity Meter ==== | ||
- | If it is necessary to move the gravity meters then they should be clamped first. | + | === Immediate needs === |
- | === Immediate needs === | + | === Plan for startup === The start up has been accomplished |
- | Restart the two gravity meters and adjust the long and cross levels. | + | |
- | === Plan for startup === | + | ==== Update from Marvin Marshak (Saturday, April 16) ==== |
- | Whenever possible, I would like to bring the meter that is supported | + | |
- | ==== Update from Marvin Marshak (Wednesday, March 30) ==== | + | |
+ | • Full electrical power was restored to the entire Soudan Laboratory TODAY. | ||
+ | DNR staff and an outside electrical contractor installed a new power cable | ||
+ | between the 22nd and 27th levels. Lab staff then checked to be sure that | ||
+ | all circuits in the lab were shut off. Following this check, power was turned | ||
+ | on to the Lab substation via the new cable. Lab staff then turned on the lights | ||
+ | and HVAC system in the Lab. These systems appear to function normally. | ||
+ | The Lab closed loop cooling system also seems to function normally. | ||
+ | The Lab fire detection system is also functioning and will shut down power | ||
+ | to the lab, in the event of an alarm detection. | ||
- | Work at Soudan continued today in both the shaft and the lab. | + | • The fiber optic cable has sufficient slack that it will be possible to cut out |
+ | the damaged section | ||
+ | be working next week. | ||
- | • Dan Bauer and Jim Beaty completed work today to stabilize | + | • Representatives of cleaning companies will visit the lab on Monday |
+ | prepare estimates for general clean up of the lab, including remnants | ||
+ | of the foam and the debris brought in by the foam. | ||
- | • New electrical cable to provide | + | • ECI, the contractor hired by the DNR to do shaft renovations, |
- | level pumps was ordered for delivery Thursday next week. | + | key personnel on site this coming week, beginning with an on-site pre-construction |
+ | meeting on Monday. CNA Engineering has also been hired to provide | ||
+ | geo-technical advice to ECI. A CNA engineer will also be on site this | ||
+ | coming week. A likely arrangement beginning this coming week is that | ||
+ | lab and DNR access to the mine will occur on a first shift, possibly beginning | ||
+ | at 6 am, with ECI shaft work on a second shift, possibly beginning at 2 pm. | ||
- | • DNR electricians installed new communications connections | + | • Work in the lab this coming week will focus on re-starting the MINOS |
- | to the 27th level shaft station. | + | Detector, beginning with checks of control system electronics and work |
+ | to dry out the magnet cables. | ||
- | • Rock removal continued in the shaft. Another new steel | + | • The sprinkler contractor has submitted drawings to the University Fire |
- | reinforcing beam was installed. An outside engineering | + | Marshal for the repairs to the sprinkler system. Approval of the drawings |
- | consultant visited Soudan and inspected | + | and repair work is also expected to start this coming week. |
- | recommended that loose rock removal | + | |
- | continue with high priority. | + | |
- | • Operations in the MINOS Lab today focused on restoring | + | • The University has hired CNA Engineering |
- | operation of monitoring | + | consultant, |
- | are scheduled | + | lab through either a ~6 inch diameter hole and/or a ~4 foot diameter hole. |
- | electrical supply system, the lab fire alarm system | + | A small hole would enable an independent path for communications, power and |
- | hard-wired telephone lines. | + | high pressure air ventilation between |
+ | hole would also enable a secondary, emergency egress, in addition to the telecom | ||
+ | and power connections. | ||