Planning next visit, Nov 27 - Dec 5. The current plan is:
Terry, Daniel and Pat will arrive on Nov 27. Pat will rent a car, Daniel will reserve the house.
Vuk will join on Nov 28 or 29, will rent a second car.
Daniel will leave on Dec 3, Vuk on Dec 4, Pat and Terry on Dec 5.
Visit all underground stations Mon-Thu. Break down the huts, but leave some of the substantial walls on 2000L and 4100L. Leave the wooden crib on 2000L. Leave the granite tiles in place in all locations.
Prepare the shipment in the Ross Warehouse: this may change, still discussing with Jaret et al, but this is the nicest place to work, has infrastructure that we could use.
Vuk will work on Work plan and decommissioning template
Gary: systematically take photos of each station. Subtleties that may be relevant for future installations, and will be helpful for a paper documenting the experiment. Photos will help preserve information, that we'll have to digest and summarize later. May be able to assess how differences in installation impact instrument performance.
Have to estimate weight of the shipment and communicate with PASSCAL to schedule the shipment.
Gary: there could be a complication with the GPS antenna, which may be impossible to do depending on the weather. We can send this later, but someone at Sanford will have to do it for us. Remember also the computer and Q330 in the IT room.
Gary: don't need to do anything with that computer, no need to back it up, leave it to PASSCAL. Vuk/Daniel agree.
Terry: will call PASSCAL when we get close to schedule the shipment.
Terry: prepare inventory, ask PASSCAL to send theirs to us. Probably best to ask Pnina - Vuk will do that.