Homestake meeting, 10/16/14
Attending:
Homestake wiki: https://zzz.physics.umn.edu/groups/homestake/home
Our agenda:
1) Homestake update
Vuk: Liteway expects to deliver 4 GPS transceivers next week, and the rest in 2-3 weeks. Should know more precisely early next week. Gary and Vuk spoke with PASSCAL, they expect to be able to send us 8 full stations in 2 weeks. Add another 1-2 weeks for shipping etc, we could start installing them around Nov 15. So, we should start making plans for another trip around that time. Could install 4-5 surface stations and 3-4 underground stations (probably focus on 4850 for the time being, maybe also try 4100-A as our best former station). Will need at least Gary and Tanner.
2) UMN test setup (Tanner)
3) Analysis of existing data