Homestake Meeting Minutes, 02/19/15
Attending:
Homestake wiki: https://zzz.physics.umn.edu/groups/homestake/home
Our agenda:
1) Homestake status
stations duty cycle
data flow
frames
2) Planning next visit: Mar 23-Apr 3
Goals:
Build and install the 4850 station near 17 ledge, including huts and the battery pad (if necessary).
Install the two 2000ft stations. Power and network should be available by the time we arrive (network is currently down).
Install the 1700 station nearest to Yates. Will not have network.
Potentially install another station at 2000, further northwest. Discussions with SURF are in progress on this.
Fix the radio issue with the water treatment plant station.
Potentially install other surface stations, depending on weather.
Improve the stability of the data flow.
3) Analysis of existing data