Go to the U of M home page
School of Physics & Astronomy
Probe Mission Study Wiki
imagerteleconnotes20180228

Telecon 20180228

Attending: Bill, Tom, Kris, Hannes, Shaul, Karl, Qi

Notes by : Qi

Agenda

Notes

  • Planck decontamination, cooling, and in-orbit checkout
    • Someone needed to write ~ 1 paragraph. Charles Lawrence suggested.
    • From Bill:
    • CPV (commissioning and performance verification) at L2
      • Telemetry checkout, cryogenic check, normal receiver operation etc.
      • For PICO, the best mode needs to be decided; spinning or spinning + precession; we have to spin to stabilize. Different spin rate is something interesting.
    • baking primary during launch to remove water not part of CPV
    • Passively cool, during the flight to L2
  • Telescope and Instrument I+T (Bill):
    • Receiver
      • Planck, did not include a lot of stuff prior to 2005
      • overview in page 1
      • some periods below:
        • Sep, 2005
          • Cryogenic chain, delivered and tested
        • Mar, 2006
          • HFI focal plane integration, 2 K bath, 100 mK, less than a week of testing; primary goal, show cryogenic works; gross noise check
        • May,2006
          • cryogenic, photometry, cooling down to 40 K, measuring surface separation
        • July,2006
          • same run as above, to do calibration, 20 day period, not fully integrated system, 2K to 100 mK, nothing at room T
          • Much longer time is better, 20 days is really risky
        • may,2008
          • final cool down, only time of fully integrated test
          • not designed to do any useful testing, cold load in front of focal plane, T is not stable, so no noise testing
        • may 2009
          • launch
    • I&T, PICO specific
      • counting back from launch, overview
        • T-4 years: devices level detectors
        • T-3years: proving sub-k cryogenics, maybe spectroscopy and noise testing;
          • the sooner you get integration tests, the better; example: problem related to wiring, you won’t know until you get the full integration
          • Planck did not have HFI+LFI fully test; 100 mK, 4K, more natural to sepaerate
          • Cryogenic photogrammetry of telescope and truss, very important for Planck
        • T-2 years: entire cooling chain
        • T-1years: require a proper chamber
      • Details:
        • T-3 years:
          • full focal plane, not the entire cooling chain
          • due to warm primary, be careful of how to mimic background operational conditions at L2
          • 3 mK fluctuation on 3K, heater, pump helium back; 10% percent level; as if we are observing CMB, for non-linearity etc.
          • no mirrors, find the right chamber, ~meter level, time being cold should not be less than 1 month
          • Polarimetric calibration ● Spectroscopic calibration
          • two runs because of some expectation of something not working
          • Planck never measured Spectroscopic with mirrors
          • Planck Polarimetric, used those obtained during device level testing; it’s tricky to do it with fully integrated system. Very difficult measurements
          • Cryogenic photogrammetry of telescope and truss [Large 300-40K chamber, 1 mo], may have to do mirrors separately for PICO, 30K, 4K
        • T-1 years:
          • cool the whole thing down, long run
          • Because of TES, optical loading, to see Psat
          • If we convince ourselves that we can do Polarimetric calibration ● Spectroscopic calibration on the whole system, we should
          • Shaul: depending on the size of chamber
          • Bill: do the math, and believe device level testings
          • Planck was lucky, given the limited time of fully integration testing.
          • Shaul: polarization modulation efficiency, one would calculate well based on the testings without mirrors.
          • Bill: angular calibration, independent may be demanding.
          • constrained bandpass mismatch, using data itself. It’s a big question to reach r<10^-4.
          • 2 month is the tight. sort of Planck schedule. better to add 1 month to do testing, not sure the cost.
          • in flight correction of HFI, the challenge is it’s difficult to do spectroscopy tests on the whole, which are in fact dependent on the whole system.
        • cost, driver, 3 level of testing set ups
          • modest, device, institutions
          • large, full focal plane, calibration equatment needed, time needed
          • 3rd, big chamber, fully integrated, time and calibration we want to test.
          • Timing is likely to drive the cost
imagerteleconnotes20180228.txt · Last modified: 2018/02/28 16:27 by kyoung