Telecon Notes 20180103

Attendance:

Notes by:

Agenda:

  • TeamX: this one is TeamX-Instrument. There is a second one in March, and also a 'Mission' one in March.
    • Our goals
      • are there any yet unidentified challenges?
      • give initial cost estimate? Our framework was ~$175M
      • Note: JPL insists on 30% cost margin; NASA guidelines are 25%.
    • Engineering Exercise
      • 3 hours/day, Dec. 19-21 total of 9 hours.
      • ~10 engineers (optics, mechanical, system engineering, cost, electronics, cooling, detectors)
    • Results
      • Awaiting final results by mid-January. All other comments are preliminary.
      • No major challenges / show stoppers identified; design is sound.
      • Cost is close to our framework under specific assumptions for the cooling.