engineering:apr8_10
Agenda for April 8, 2010
Integration
Refine cost and schedule
Improve the conceptual design of the FAARM
Water Shield
Make it real, talk to companies, do the engineering e.g.
Door or labyrinth
Acrylic tunnel costs
Outer tank engineering
Develop infrastructure into shield (ductwork, electrical etc)
Screener Group
Work with Yuen-Dat to compile results of survey
Define parameters of shielding and common elements between screeners
Plan for screening at Sanford and schedule of installation and move
Immersion Tank
Continue cost and schedule for CTF
Characterization
short term plans for this summer - involve other groups
long term plans for neutron work