Agenda for April 8, 2010
* Anything further needed before April 12?
* Sent around Schedule: posted in [[:groups|Working Groups]]
* Working Group Jobs. Next Milestone is the July 13-15 NSF review
Water Shield Questions
Make it real, talk to companies, do the engineering e.g.
Door or labyrinth
Acrylic tunnel costs
Outer tank engineering
Integration
Refine cost and schedule
Improve the conceptual design of the FAARM
Screener Group
Work with Yuen-Dat to compile results of survey
Define parameters of shielding and common elements between screeners
Plan for screening at Sanford and schedule of installation and move
Immersion Tank
Continue cost and schedule for CTF
Characterization
short term plans for this summer - involve other groups