1) Homestake update
planning next visit: Sep 21-27
status of various orders:
GPS units: ordered 25 transceivers and 10 splitters. Expect 6 week delivery, hoping to get a few units earlier than that, for tests during the next visit to Homestake
fiber: ordered 13000', should be delivered within 1 week
network components: ordered network switches, media converters, boxes to house equipment etc, expect delivery within 1 week
poly panels: ordered ~50 panels, should already be delivered at Homestake
granite tiles: still have not heard back from Homestake, will probably purchase several at MSP
anything for surface stations?
status of various documents (MOU, Exp. Planning Statement, Insurance certificates)
2) UMN test setup (Tanner): setting up the equipment in the new lab, and writing down a procedure to streamline it for Homestake. Then will focus on streaming the data.
3) Analysis of existing data
Estimation algorithms (Shivaraj, Eric, Noah):
Noah's S-wave study: corrected the error (different velocity used in injection and recovery), and reproduced different tests discussed at the last meeting. Correctly recover injection position, shows strong dependence on scale of the array (or equivalently on the frequency of the wave), as well as on the array configuration. Changing polarization can change the shape of the recovered blob, but the blob is typically well centered.