Homestake Meeting Minutes, 10/06/2016
Attending: Levi, Vuk, Gary, Daniel, Victor, Pat, Terry
Agenda:
Homestake array update
Daniel: removed all surface stations, everything in boxes in cold storage. Tried to pack everything so that in December the boxes can be simply added. Has inventory sheet, will add it to the wiki. Pallets are there (4 of them) in cold storage, two of them already used for surface stations (but can probably add to them). Pick them up with a forklift. Hope to bring the truck to the cold storage, via a different gate/road that may be even easier for the truck to go through.
Gary: Connector came off the antenna at RR station, not sure how that happened. Probably wasn't installed right.
Daniel: timing slowly drifted off at this station, got a timing lock at the decommissioning, so could try to get a linear correction.
Gary: for the archive they will flag it, but we should be able to do better, and make new miniSEED files that have the corrected data. Not sure how large the correction will need to be, probably of order 1 second.
Daniel: for some applications where timing matters, maybe we just not use this station. Vuk/Gary agree.
Daniel: Gary and Daniel have a copy of the baler data.
Gary/Vuk: probably best to wait until December to get baler data for underground stations, and deal with it all then.
Data analysis
Gary: looking at data from the land-streamer, to figure out the time. The likely reason this is so difficult is that the engine of the truck and hydraulics was significant, making the noise correlated among different stations (including deep underground stations). This makes it difficult to make correlations to determine the timing. All of this is tens of Hz. This is a hypothesis, should look at it more…