Sunday (eg Nov 27): arrive mid-day and access the storage to prepare a few boxes for Monday.
Monday: visit 4100 and uninstall 3 stations. Leave panels at Yates for the night crew to bring to surface
Tuesday: visit 1700/2000 and uninstall 6 stations. Leave Yates panels AND instrument boxes at Ross and 1700 panels at Yates for the night crew
Wednesday: visit 4850 and uninstall 4 stations. Leave panels at Yates.
Thursday: visit 800 and 300 and uninstall the two stations. Leave panels at Yates, or bring them out ourselves.
This would give us Friday and the weekend to clean up the equipment, stuff the boxes, do inventory, and prepare the pallets.
Issue:
We might not be able to handle 2000 and 1700 in one day. In this case, maybe we could split up and have 2 crews on Thursday, one to finish off 2000 and the other to uninstall 800 and 300.
Some old stations have old equipment, as well as panels on the walls, so they may take more time to clean up.
Can we get motors on each level, question for SURF.
Data analysis